Key metrics
Product | Typical dimensions |
| Length | 12.5 m |
| Width | 3.5 m |
| Height | 3.5 m |
All Plant & Equipment Modules (PEMs) come fully wired to isolator’s or BMS panel. A recent study of our PEM’s solution, which had 90% of the services modularized (final site connections required post-delivery) demonstrated a 60% productivity improvement in installation on site.
- Heating and cooling: heat pumps (air/water/ground), CHW/LTHW generation, thermal stores, plate heat exchangers
- Energy systems: CHP, boilers (gas/oil/electric), flues and dilution systems, BEMS integration, metering
- Water systems: cold water storage, booster sets, filtration and treatment, softeners, dosing
- Supports main plant items such as pumps, chillers, fans, plate heat exchangers and Electrical switch panels
- Electrical switch panels, ATS, Harmonic Filters
- Electrical and controls: distribution boards, control panels, BMS field devices, fire alarm interfaces, emergency lighting in plant space
- Full Electrical and controls wiring installation, testing and certification
- Ancillaries: chemical dosing, pressurisation units, expansion vessels, strainers, valves, gauges, drip trays, leak detection
- Structural/support: skid frames, bases, lifting frames, vibration isolation, builder work details for openings and plinths
- DfMA-led engineering using repeatable standard modules adapted to project-specific requirements
- BIM-enabled coordination (3D/4D/5D)
- Maintainability embedded at concept and detail stages
- Commissioning strategy embedded throughout concept and detail stages
- Early engagement to confirm operational requirements and redundancy levels
- Building Regulations, BS, EN and CIBSE guidance
- Pressure Equipment Safety Regulations, PED/UKCA and water regulations
- BS EN 12845 and healthcare HTMs where applicable
- BS 7671 electrical compliance
- Controlled factory environment with testing and QA stage gates.
- FAT documentation and BIM aligned asset labelling.
- UKCA/Kitemark where applicable and full traceability.
- BS 99001 / ISO9001 Quality management
- Factory production EN 1090-2:2009+A1:2011 to Execution Class 3(EX3)
- Just-in-time delivery and lift planning
- Pre-agreed structural interfaces and hook-up methodology
- Fully inspected and electronically auditable QC records
- Cx Level Test Scrips and Factory Acceptance Witnessing
- FAT testing and full documentation package available
- Programme certainty
- Improved quality and reliability
- Solutions integration
- Reduced site risk and disruption
- Simplified maintenance