London Data Centre 5, Slough

Client
Major global data centre/collocation provider
Services
Data Solutions
Duration
February 2013 - November 2013

Full Project Details

Crown House Technologies (CHt) was selected as principal contractor to deliver 16,000 m² of technical (whitespace) over two floors, with a further 8,000m² of plant space for UPS/switchgear and AHUs on the second floor.

Our role

LD5, a colocation data facility in the Thames Valley ‘tech’ corridor, has been developed for a US data client over several years, and the fit out of the final phase of 7000m2 of fallow space, plus supporting plant and infrastructure, began in February 2013.

The challenge

The works also consisted of the construction of external HV switchrooms, pump rooms and generator rooms together with an external screened gantry for the chillers. Our delivery approach was achieved under a fast track programme, facilitated by the Group’s modular design strategy. Utilising Digital Engineering methodology and modular components from Crown House  Manufacturing in Oldbury, green design and energy efficiency were at the heart of the design principles for LDC5, with the client commercially and corporately highly-driven to improve on existing sites. The data centre industry faces increasing scrutiny of its carbon footprint, and developing the most green and energy efficient design possible is of mutual benefit to the client and its customers and the environment.

CHt’s ‘Mission Zero’ objective was 100% achieved with not a single incident or accident. Matching the success on site has been a highly successful community programme, with several site members and suppliers donating time and materials to a number of local initiatives.

The engineering behind our delivery

UPS

The UPS system uses a distributed load philosophy, minimising the number of units needed to provide the requisite level of resilience. This has the benefit of increasing the average load on each unit, pushing them into their peak efficiency operating region at the design load of 75%. Minimising the number of units also has reduced embodied energy implications, requiring fewer materials in manufacture and less transport. At site, this means fewer cables and less building space required, all with reduced embodied energy implications.  

Free Cooling Air Cooled Chillers

Air cooled chillers with free cooling coils are used in the design. This improves efficiency for the proportion of the year when ambient temperatures are low enough to provide cooling without running compressors.  

Fresh Air Cooling

The second floor of the building houses the majority of the electrical plant, including the UPS, associated switchgear and step down transformers. A fresh air cooling design has been developed for the concept which provides highly-efficient free cooling for the significant portion of the year when this is available, minimising the amount of mechanical cooling required. Expected energy savings over conventional methods of cooling this load are in the order of 95%. This load represents a worst case of approximately 8% of the total cooling load, meaning that total site-wide cooling energy consumption  is reduced by approximately 6-7%.